Field & Maintenance Services

The Swachh Bharat Mission was initiated by Prime Minister Narendra Modi on 2 October 2014, with a resolution to achieve Open Defecation Free (ODF) India by 2 October 2019. The task was to build toilets and to bring necessarybehavioural change among the community towards open defecation. Mumbai the financial capital of India has been fighting open Defecation since long. To put an end to open Defecation and to speed up this process the Municipal Corporation of Mumbai decided to install Portable Community Toilets at different locations in Mumbai. Many private companies joined hands with BMC under Corporate Social Responsibility (CSR) to participate in this campaign. 

 

Case Study

Around 50 Community Toilets of different sizes were ordered to MK Portable. These ready to use portable toilets were fitted with all required plumbing accessories. Special attention was given towards the strength and stability of these porta toilets as a majority of these toilets were to be installed in Slum areas. MK Portable was proud to be a part of this cleanliness mission by the Municipal Corporation of Mumbai.

 

MK Portal follows industry standard protocol for Manufacturing of its Portable Cabins and containers. However material specifications may vary from cabin to cabin depending upon their usage. Given below is a material specification for our standard product:

Sr.No. Components Description
1 TOP FRAME 50mm X 50mm MS Sq. Pipe or 75mm x 75mm MS Sq. Pipe
2 BOTTOM FRAME 150mm X 75mm “I” Beam (5mm Thick)
3 STIFFENER TOP 40 x 20 M.S.Sq.Pipe  
4 STIFFENER BOTTOM 150mm x 75mm “I” Beam (5mm Thick)
5 SIDE POST 75mm X 75mm Angle (5mm Thick)
6 SIDE WALL STIFFENERS (Internal) Specially formed 1.2mm C.R.C. Post Section – 18SWG
7 PANELLING OUTSIDE Corrugated G.I Sheet- 1.2mm thick or Corrugated M.S Sheet- 1.2mm
8 INTERNAL WALL PANELLING 9mm Both Side Laminated Particle Boards
9 ROOF OUTSIDE G.I  Sheet- 1.2mm or M.S Sheet 1.2mm Thick thick Properly Sloped & Water Tight
10 False Ceiling 9mm Both Side Laminated Particle Boards
11 BOTTOM FLOORING 18mm Cement Board with Vinyl Carpet
12 ALUMINIUM WINDOWS Double Shutter Sliding Aluminum Powder Coated Windows Tinted Glass with Safety Grills
13 DOOR Insulated with for locking agreement, hold draft & handles
14 INSULATION Glass Wool /Rockwool Insulation-(Side Wall-50mm), (Ceiling -50mm) 48Kg Density
15 WIRING All wiring shall be concealed type & shall be of PVC insulated copper wire (KEI).
16 ELECTRICAL MATERIAL All electrical fittings in the Portable Cabin shall be 220-240V, AC 50Hz, and Switch Socket, Light, telephone, Fans, Split AC point etc. ALL ISI MARKED.
17 OUTSIDE PAINTING Phosphate the Cabin & Painting with 1 coat of Epoxy Primer with 2 Coat of Epoxy Paint.
18 LEGS 5 inch Height, Four Legs at all four corners.
19 HOOKS Specially formed Hooks for Easy Lifting & Shifting
20 PARTITION WALL(WHEREVER APPLICABLE) MS Pipe Stiffener with 8mm MDF

 

MK Portal cabins come preloaded with some standard accessories and fitments. Given below are details and quantities of MK Portal standard accessories:

Sr. No. Content 10ft 20ft 40ft
1 Provision for Split A/C 1 1 2
2 3 ‘ x 3 ‘ sliding window 3 4 6
3 6’1/2” x 3′ doors 1 1 2
4 Paneling on all sides (including ceiling) of  Decorative Laminated Particle board As per size As per size As per size
  Electrical fittings      
5 Light 4 6 10
6 Fan 1 3 6
7 External bulk head light 1 1 2
8 15 Amp switch & sockets 1 2 4
9 5 Amp switch & sockets 4 6 10
10 Electrical switch boards inside 1 1 2
11 Main switch Inside the container with Box 1 1 1
12 Wall to wall vinyl flooring As per size As per size As per size